Progress continues on our new campus! Get the latest update at our Congregational Meeting this Sunday, May 15, at 1 PM on Zoom. Register to join us at uuca.org/maymeeting

The high ceiling in the sanctuary will start being painted next Wednesday. This week, we’ve started work on lights in the grid area. The wood grain wall cover will begin installation on Monday the 23rd. Choate hopes to start stage framing on May 30th.

The grid lights on the second floor are done and ready for inspection. Friday of this week or Monday of next, teams will start laying ceiling tile. The carpet is on track for Wednesday of next week. Bathroom accessories will be installed on Monday, May 30th.   The elevator wrap-up will be finished by Monday or Tuesday at the latest, and then teams will begin masonry and electric work to finish it.

Sheetrock ceilings will continue installation through Monday and Tuesday of next week. The floor tile will begin on Wednesday of next week. Next Thursday and Friday, teams will begin polishing concrete.

HVAC startup of the cassettes (air conditioning room vents) is today. The other HVAC should be up on Monday of next week. Stripping is done in the parking lot. The dirt and stone in the ADA ramp by the playground will be filled on Monday and Tuesday. Sidewalks continue development through the rest of the month. The plumber has started working on the waterline.

As the OAC meeting closed, the fire marshal arrived and gave his initial blessing to have a temporary occupancy permit for the wing building. We still would need the building inspector’s blessing. The way the county treats a temporary occupancy permit is that furniture can be moved in, staff can work, and training can occur. No public access is allowed.