The site demolition continues with most of the action having moved over to the 1968 building (education wing).  A lot of the demo of the first floor of the administration wing has also been completed. By the end of day on Monday, we expect the major demolition and asbestos abatement to be completed.

We’ve asked CCCA to get a finishes meeting on the schedule in September due to the long lead times on some materials. The schedule is holding and no surprises continue to bless our process! In general submittals and RFI’s have been flying through the systems. We’re processed anywhere from 30-70 emails a day back and forth during the week as Choate, CCCA and the subs all coordinate requests and plan.

Stay tuned for more updates!