We are currently in the demolition phase!

The Sanctuary is substantially complete, as shown in photos below. The next steps in the Sanctuary will be to increase the shoring of the ceiling and bracing of the scissor trusses before removing the sheetrock, which is currently adding support.  This will allow mechanical and engineering folks to get more precise measurements so that fabrication can get underway.

The admin wing has some initial and safe demo happening.  They’ve ripped out ceiling tiles and insulation, but next week demo of admin begins in earnest.  After the demo, then we will be looking at concrete cuts for elevator and plumbing.

Atlanta Gas and Light has cut off our gas lines as requested, and Georgia Power has established temporary power for Choate.

Progress continues and spirits are high!

]